PART 7 MISCELLANEOUS AND GENERAL
STREETS TO BE PERMANENTLY STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
2.(1) Without prejudice to the generality of paragraph 1, the...
3.(1) Without limitation on the scope of paragraph (1), the...
5.For section 7 of the 1965 Act (measure of compensation)...
7.The following provisions of the 1965 Act (which state the...
10.Section 22 of the 1965 Act (interests omitted from purchase)...
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1.For the protection of the utility undertakers referred to in...
2.In this Part of this Schedule— “alternative apparatus” means alternative...
5.Regardless of any provision in this Order or anything shown...
7.(1) Where, in accordance with the provisions of this Part...
8.(1) Not less than 28 days before starting the execution...
9.(1) Subject to the following provisions of this paragraph, the...
10.(1) Subject to sub-paragraphs (2) and (3), if by reason...
11.Nothing in this Part of this Schedule affects the provisions...
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 4 FOR THE PROTECTION OF NORTHERN POWERGRID (YORKSHIRE) PLC
32.For the protection of Northern Powergrid the following provisions have...
33.In this Part of this Schedule— “alternative apparatus” means alternative...
34.This Part of this Schedule does not apply to apparatus...
35.Regardless of any provision in this Order or anything shown...
37.(1) Where, in accordance with the provisions of this Part...
38.(1) Not less than 35 days before starting the execution...
39.(1) Subject to the following provisions of this paragraph, the...
40.(1) Subject to sub-paragraphs (2) to (4), if by reason...
41.Nothing in this Part of this Schedule affects the provisions...
42.Where in consequence of the proposed construction of any of...
43.If in consequence of an agreement reached in accordance with...
44.The plans submitted to Northern Powergrid by the undertaker pursuant...
45.Where practicable, the Undertaker and Northern Powergrid will make reasonable...
PART 5 FOR THE PROTECTION OF RAILWAY INTERESTS
46.The provisions of this Part of this Schedule have effect,...
47.In this Part of this Schedule— “asset protection agreement” means...
48.(1) Where under this Part of this Schedule Network Rail...
49.(1) The undertaker must not exercise the powers conferred by—...
50.(1) The undertaker must before commencing construction of any specified...
52.The undertaker must— (a) at all times afford reasonable facilities...
53.Network Rail must at all times afford reasonable facilities to...
54.(1) If any permanent or temporary alterations or additions to...
55.The undertaker must repay to Network Rail all reasonable fees,...
56.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
58.The undertaker must not provide any illumination or illuminated sign...
59.Any additional expenses which Network Rail may reasonably incur in...
60.(1) The undertaker must pay to Network Rail all reasonable...
63.The undertaker and Network Rail may, subject in the case...
64.Nothing in this Order, or in any enactment incorporated with...
65.The undertaker must give written notice to Network Rail if...
PART 6 FOR THE PROTECTION OF CADENT GAS LIMITED