SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Water Resources Assessment

schedule 2 paragraph 8 8.—(1) No part of the energy park works may commence, save for the preliminary works, until a Water Resources Assessment is submitted to and agreed with Anglian Water following consultation with the Environment Agency on matters relating to their function and subsequently approved by the relevant planning authority. The Water Resources Assessment will include a scheme to deal with the supply of water during both construction and operation of the authorised development including final process design, maximum daily demand, and water efficiency measures.

(2) The scheme submitted and approved under sub-paragraph (1) must be in accordance with the environmental statement and for the operational water supply must be included in the operational environmental management plan submitted pursuant to Requirement 4(5) – (7) and for the construction water supply must be included in an update to the construction environment management plan submitted pursuant to Requirement 4(2).

(3) The scheme approved under sub-paragraph (1) must be implemented as approved throughout the construction and operation of the energy park works unless agreed otherwise by the relevant planning authority following consultation with the Environment Agency and Anglian Water as necessary.

(4) For the purposes of this Requirement—

schedule 2 paragraph 8 4 a (a)term anglian water Anglian Water” means Anglian Water Services Limited, the statutory water supply provider for the North Lincolnshire Green Energy Park under the Water Industry Act 1991 and responsible for ensuring the cumulative impacts of development do not compromise the supply of water for domestic purposes; and

schedule 2 paragraph 8 4 b (b)term water resources assessment Water Resources Assessment” includes all designs, drawings, specifications, resource assessments, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the source and supply of water for construction and operation.