SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
New highway access
schedule 2 paragraph 15 15.—(1) The undertaker must not commence development of the energy park works or railway reinstatement works, excluding any preliminary works, until the new access road (Work No. 5) has been constructed to base course level and connected to the public highway.
(2) As part of constructing the new access road to base course level under sub-paragraph (1), the undertaker must carry out such parts of Work Nos. 10 and 11 as fall within the land in respect of which Work No. 5 is authorised.
(3) Prior to the energy recovery facility (Work No. 1) coming into operation the undertaker must complete the new access road (Work No. 5) to the reasonable satisfaction of the relevant planning authority, in consultation with the relevant highway authority, and make it available for public use.