SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Decommissioning
schedule 2 paragraph 17 17.—(1) Within two years of the date that the undertaker decides to end commercial operation of the energy park works, the undertaker must submit to the relevant planning authority for its approval a decommissioning plan, including a timetable for its implementation and a decommissioning environmental management plan which shall include, but not be limited to, matters such as flood risk.
(2) The plan submitted to and approved under sub-paragraph (1) must be implemented as approved unless otherwise agreed with the relevant planning authority.