SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Combined heat and power
schedule 2 paragraph 18 18.—(1) No part of the energy park works may be commissioned until a scheme for the provision of steam or hot water pass-outs has been submitted to and approved by the relevant planning authority.
(2) The scheme submitted under sub-paragraph (1) must as a minimum comply with the conditions relating to steam and hot water pass-outs within any environmental permit granted in respect of the authorised development.
(3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the coming into operation of the authorised development and maintained throughout the operation of the authorised development.
(4) Prior to the energy park works coming into operation, the undertaker will construct the northern spur.
(5) No later than the date that is 18 months after the date of the energy park works coming into operation, the undertaker must submit to the relevant planning authority for its approval a report (“the CHP review”) updating the combined heat and power assessment.
(6) The CHP review submitted must—
schedule 2 paragraph 18 6 a (a)consider the opportunities that reasonably exist for the export of heat from Work No. 11 at the time of submission of the CHP review; and
schedule 2 paragraph 18 6 b (b)include a list of actions (if any) that the undertaker is reasonably and practicably able to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 11.
(7) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
(8) The relevant planning authority must consult with the Environment Agency before approving any CHP review.