SCHEDULE 14PROTECTIVE PROVISIONS
PART 5FOR THE PROTECTION OF RAILWAY INTERESTS
schedule 14 paragraph 53 53. Network Rail must at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.