SCHEDULE 9Protective provisions

PART 12For the protection of Immingham Oil Terminal operators

Notice of works

169.  The undertaker must provide to the IOT Operators a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions. The IOT Operators will be entitled to watch and inspect the execution of the relevant works at any time.