SCHEDULE 2Requirements

PART 1Requirements

Landscape and ecological management plan

11.—(1) Subject to sub-paragraph (4), no stage of the authorised development may commence until a LEMP for that stage, substantially in accordance with the outline landscape and ecological management plan, has been submitted to and approved by the relevant planning authority in consultation with Lincolnshire County Council.

(2) The LEMP must include:

(a)an implementation timetable; and

(b)measures for the protection of existing features adjacent to the Works as detailed in the Environmental Statement.

(3) Each stage of the authorised development must be implemented in accordance with the approved LEMP for that stage.

(4) Sub-paragraph (1) only applies to those stages of the authorised development in respect of which any landscape and ecological management measures are to be implemented by the undertaker, as identified in the outline LEMP.