PART 3Streets
Agreements with street authorities
15.—(1) A street authority and the undertaker may enter into agreements with respect to—
(a)the construction of any new street including any structure carrying the street over or under any part of the authorised development;
(b)the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;
(c)any stopping up, alteration or diversion of a street authorised by this Order; or
(d)the carrying out in the street of any of the works referred to in article 9 (street works).
(2) Such an agreement may, without prejudice to the generality of paragraph (1)—
(a)make provision for the street authority to carry out any function under this Order which relates to the street in question;
(b)include an agreement between the undertaker and street authority specifying a reasonable time for completion of the works; and
(c)contain such terms as to payment and otherwise as the parties consider appropriate.