ID badges: Hide | Show

PART 3Streets

Agreements with street authorities

article 15 15.—(1) A street authority and the undertaker may enter into agreements with respect to—

article 15 1 a (a)the construction of any new street including any structure carrying the street over or under any part of the authorised development;

article 15 1 b (b)the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;

article 15 1 c (c)any stopping up, alteration or diversion of a street authorised by this Order; or

article 15 1 d (d)the carrying out in the street of any of the works referred to in article 9 (street works).

(2) Such an agreement may, without prejudice to the generality of paragraph (1)—

article 15 2 a (a)make provision for the street authority to carry out any function under this Order which relates to the street in question;

article 15 2 b (b)include an agreement between the undertaker and street authority specifying a reasonable time for completion of the works; and

article 15 2 c (c)contain such terms as to payment and otherwise as the parties consider appropriate.