SCHEDULES
SCHEDULE 11DEEMED MARINE LICENCE UNDER THE 2009 ACT—GENERATION ASSETS
PART 2CONDITIONS
Completion of construction
25.—(1) The undertaker must submit a close out report to the MMO, MCA, UKHO and the statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
(a)the final number of installed wind turbine generators;
(b)a plan of the layout of installed wind turbine generators;
(c)latitude and longitude coordinates of the centre point of the location of each wind turbine generator provided as Geographical Information System data referenced to WGS84 datum;
(d)latitude and longitude coordinates of the inter array cable routes provided as Geographical Information System data referenced to WGS84 datum; and
(e)the installed wind turbine generator parameters relevant for seascape, landscape and visual impact.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.