SCHEDULES
SCHEDULE 11DEEMED MARINE LICENCE UNDER THE 2009 ACT—GENERATION ASSETS
PART 2CONDITIONS
Reporting of engaged agents, contractors and vessels
15.—(1) The undertaker must provide the following information to the MMO—
(a)the name and function of any agent or contractor appointed to engage in the authorised scheme no less than 24 hours before the agent, contractor or subcontractor carries out any part of the authorised scheme; and
(b)each week during the construction of the authorised scheme a completed Hydrographic Note H102 listing the vessels currently and to be used in relation to the authorised scheme.
(2) Any changes to the name and function of the specified agent, contractor or subcontractor that will carry out the specified licenced activities or vessel to be used must be notified to the MMO in writing prior to the agent, contractor, subcontractor or vessel carrying out the relevant part of the authorised scheme.
(3) The undertaker must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to any agents, contractors or subcontractors that will carry out the part of the authorised scheme on behalf of the undertaker prior to them carrying out any licensed activity.