SCHEDULES
SCHEDULE 10PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF RAILWAY INTERESTS
8. The undertaker must—
(a)at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b)supply the engineer with all such information as they may reasonably require with regard to a specified work or the method of constructing it.