SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Detailed offshore design parameters
5.—(1) The total number of cable circuits must be no more than four.
(2) The total length of the cable circuits comprising Work No. 2 must be no more than 250 kilometres.
(3) The total volume of cable protection comprising development associated with Work No 2 must be no more than 175,000 cubic metres with a maximum footprint of 300,000 square metres.
(4) The number of cable crossings comprising Work No. 2 must be no more than four unless otherwise agreed with the MMO.
(5) The maximum area impacted by cable crossings must be no more than 10,000 square metres.
(6) The total volume of cable protection for cable crossings must not exceed 20,000 cubic metres (pre- and post-lay).
(7) The total length of the cable circuits comprising Work No. 3(b) must be no more than 40 kilometres.
(8) The total volume of cable protection comprising development associated with Work No 3(b) must be no more than 110,500 cubic metres with a maximum footprint of 122,000 square metres.
(9) The total length of cable circuits comprising Work Nos 3(b), 4 and 5 together must be no more than 170 kilometres.
(10) The total volume of cable protection comprising development associated with Work Nos. 4 and 5 must be no more than 470,000 cubic metres with a maximum footprint of 517,000 square metres.