SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Crossing Schedule
44.—(1) No stage of the authorised development within the Order limits landward of MLWS (excluding any onsite preparation works) may commence until a trenchless crossing plan showing the final locations and extent of each trenchless crossing in that stage and its compound has been submitted to and approved by the relevant planning authority in consultation (where relevant) with West Sussex County Council, the Environment Agency, Southern Water and the relevant statutory nature conservation body.
(2) The undertaker must submit alongside the trenchless crossing plan, detailed feasibility assessments, supported by local ground investigation data, for trenchless crossings through irreplaceable habitats, sites of special scientific interest and sensitive landscape features within South Downs National Park.
(3) The trenchless crossings in the relevant stages must be undertaken in accordance with the approved details.