SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
National Park enhancement and furtherance
41.—(1) The authorised project must not be commenced, save in respect of onshore site preparation works, until a National Park enhancement and furtherance scheme in accordance with the National Park enhancement and furtherance principles document has been submitted to and approved by South Downs National Park Authority.
(2) The National Park enhancement and furtherance scheme must set out appropriate measures to compensate for the impact of the authorised development on the South Downs National Park and seek to further the statutory purposes of the South Downs National Park as set out in section 5 of the National Parks and Access to the Countryside Act 1949.
(3) The National Park enhancement and furtherance scheme must be implemented as approved.