ID badges: Hide | Show

SCHEDULES

SCHEDULE 1AUTHORISED PROJECT

PART 3REQUIREMENTS

Coastal erosion

26.—(1) No works comprising Work Nos. 6 or 7 may commence until a coastal erosion and future beach profile estimation assessment has been carried out and a scheme identifying any mitigation or adaptive management measures required to help minimise the vulnerability of this part of the Order land from future coastal erosion and tidal flooding (if required) has been submitted to and approved in writing by the Environment Agency.

(2) Any mitigation or adaptive management measures identified as part of the scheme submitted pursuant to (1) above must be implemented as approved.