SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Construction traffic management plan
24.—(1) No stage of the authorised project within the onshore Order limits landwards of MLWS may commence until written details of—
(a)a construction traffic management plan (which accords with the outline construction traffic management plan); and
(b)a construction workforce travel plan (which accords with the outline onshore construction workforce travel plan),
for the stage have each been submitted to and approved by the highway authority following consultation with the relevant planning authority.
(2) The construction traffic management plan must include, as a minimum—
(a)a routeing plan to secure that heavy goods vehicles (HGVs) used during the construction period are to avoid settlements, the Air Quality Management Area in Cowfold and the A24 through Findon wherever possible;
(b)management of junctions and crossings of the public highway; and
(c)measures for laying cable circuits in streets by either single lane control or short road closure depending on the location.
(3) Any construction traffic management plan submitted under sub-paragraph (1)(a) or construction workforce travel plan submitted under sub-paragraph (1)(b) may cover one or more stage of the onshore works.
(4) The construction traffic management plan for each stage must be implemented as approved.
(5) The onshore construction workforce travel plan for each stage must be implemented as approved.