SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Biodiversity net gain
14.—(1) No stage of the authorised project within the onshore Order limits (excluding any onshore site preparation works) may commence until—
(a)a biodiversity net gain strategy for that stage which accords with the outline biodiversity net gain information comprising Appendix 22.15 of the Environmental Statement has been approved in writing by the relevant planning authority in consultation with Natural England; and
(b)at least 70% of the total number of biodiversity units as required for that stage of the development have been secured and where appropriate proof of purchase provided in accordance with the approved biodiversity net gain strategy and to the satisfaction of the relevant planning authority in consultation with the statutory nature conservation body.
(2) The location for delivery of biodiversity units is to follow a prioritisation exercise, as described in Appendix 22.15 of the Environmental Statement, with priority given to areas inside or within close proximity to the proposed DCO limits.
(3) The biodiversity net gain strategy for each relevant stage must be implemented as approved.
(4) Any remaining shortfall in biodiversity units identified following detailed design will be secured prior to construction works being completed.
(5) Any biodiversity net gain strategy under sub-paragraph (1) may cover one or more stages of the onshore works.