SCHEDULE 8PROTECTIVE PROVISIONS

PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES

Final certificate

64.—(1) No sooner than 12 months from the date of issue of the provisional certificate the undertaker must apply in writing to the relevant highway authority for a final certificate in respect of the specified works.

(2) Following receipt of the application for a final certificate, the relevant highway authority must as soon as is reasonably practicable—

(a)inspect the specified works; and

(b)provide the undertaker with a written list of any further works required to remedy or make good any defect or damage in the local highway network, or confirmation that no such works are required for this purpose.

(3) The undertaker must carry out such works notified to it pursuant to sub-paragraph (2).

(4) The relevant highway authority must promptly issue the final certificate to the undertaker once the relevant highway authority is reasonably satisfied in relation to the specified works that—

(a)any defects or damage arising from defects during the maintenance period and any defects notified to the undertaker pursuant to sub-paragraph (2) and any remedial works required as a result of the stage 4 road safety audit have been made good to the reasonable satisfaction of the relevant highway authority;

(b)the costs have been paid to the relevant highway authority in full;

(c)the undertaker has provided the relevant highway authority with a health and safety file in respect of the specified works to the relevant highway authority’s reasonable satisfaction; and

(d)the undertaker has provided the relevant highway authority with such detailed design information as the relevant highway authority has requested (acting reasonably) in relation to the specified works as built.

(5) The issue of a final certificate by a relevant highway authority amounts to an acknowledgment by the relevant highway authority that the construction alteration or diversion (as the case may be) of a highway has been completed to its reasonable satisfaction for the purposes of article 12 (construction and maintenance of new, altered or diverted streets) of this Order.

(6) On the issue of the final certificate to the undertaker the bond is to be released in full.