SCHEDULE 8PROTECTIVE PROVISIONS
PART 3FOR THE PROTECTION OF LONDON LUTON AIRPORT OPERATIONS LIMITED
19.—(1) The provisions of this Part of this Schedule—
(a)have effect unless otherwise agreed in writing between the undertaker and LLAOL; and
(b)cease to have effect where LLAOL is no longer the airport operator.
(2) For the period that LLAOL is the airport operator, the undertaker must not—
(a)in relation to land shown within the airport boundary plan (existing), exercise any power under this Order except with the consent of LLAOL (including, for the avoidance of doubt, the service of notice to Luton Borough Council in accordance with article 44(1) (interaction with LLAOL planning permission) of the Order); and
(b)exercise any power under this Order in a manner which would compromise the safe and efficient commercial operation of the airport by LLAOL except with the consent of LLAOL; or
(c)commence the construction of Works Nos. 6b(01), 6b(02) and 6b(03), until a written notice of the works comprising Works Nos. 6b(01), 6b(02) and 6b(03) has been given to LLAOL at least 56 days prior to commencement.