Provisional certificate

42.—(1) Following any closure or partial closure of any of the strategic road network for the purposes of carrying out the specified works, National Highways will carry out a site inspection to satisfy itself that the strategic road network is, in its opinion, safe for traffic and the undertaker must comply with any reasonable requirements of National Highways prior to reopening the strategic road network.

(2) As soon as the undertaker considers that the provisional certificate may be properly issued it must apply to National Highways for the provisional certificate.

(3) Following an application for a provisional certificate, National Highways must as soon as reasonably practicable—

(a)inspect the specified works; and

(b)provide the undertaker with a written list of works that are required for the provisional certificate to be issued or confirmation that no further works are required for this purpose.

(4) When—

(a)a stage 3 road safety audit for the specified works has been carried out and all recommendations raised including remedial works have (subject to any exceptions agreed) been approved by National Highways, such approval not to be unreasonably withheld or delayed;

(b)the specified works incorporating the approved remedial works under sub-paragraph (4)(a) and any further works notified to the undertaker pursuant to sub-paragraph (3)(b) have been completed to the reasonable satisfaction of National Highways;

(c)the as built information has been provided to National Highways; and

(d)the undertaker has paid the commuted sum to National Highways,

National Highways must promptly issue the provisional certificate.

(5) The undertaker must submit a stage 4 road safety audits as required by and in line with the timescales stipulated in the road safety audit standard.

(6) The undertaker must comply with the findings of the stage 4 road safety audit and must pay all reasonable costs of and incidental to such and provide updated as-built information to National Highways.