7. The elements of the authorised development listed in columns (1) and (2) of the table below must not exceed the maximum dimensions and levels (as applicable) set out in relation to that element in columns (3) to (6) of that table.
(1) Element of authorised development | (2) Work No. | (3) Maximum building height (metres) | (4) Maximum parameter height (metres AOD) | (5) Maximum work area (m 2) | (6) Maximum volume in m 3) | (7) Notes |
---|---|---|---|---|---|---|
Airfield equipment – Surface Movement Radar | 2a(02) | 14.3 | 176.2 | 5,017 | 7,508 | N/A |
New Airfield Equipment Instrument Runway Visual Range (IRVR) | 2b(02) | 3.3 | 163.7 | 37,300 | 123,090 | N/A |
Fire Training Ground | 2d | 15.4 | 177.8 | 87,346 | 423,500 | N/A |
Existing Engine Run Up bay updates | 2e | 4.4 | 159.4 | 16,025 | 67,320 | N/A |
Engine Run Up bay | 2f | 13.2 | 166.8 | 12,525 | 132,000 | N/A |
Relocated Engine Run Up bay | 2g | 13.2 | 166.6 | 11,512 | 132,000 | N/A |
Terminal 1 New Pier C and External Canopy | 3a(01) | 16.5 | 173.7 | 4,133 | 44,616 | N/A |
Terminal 1 Immigration extension | 3a(02) | 9.4 | 167.6 | 270 | 2,525 | N/A |
Terminal 1 Departure Lounge South extension | 3a(03) | 18.7 | 171.1 | 957 | 12,155 | N/A |
Terminal 1 Departure Lounge North extension | 3a(04) | 9.4 | 171.4 | 400 | 3,740 | N/A |
Terminal 1 Baggage Hall extension | 3a(05) | 11.6 | 164.0 | 1,104 | 9,221 | N/A |
Terminal 2 | 3b(01) | 26.5 | 180.5 | 30,470 | 672,067 | N/A |
Terminal 2 extension | 3b(02) | 26.5 | 180.5 | 10,635 | 212,689 | N/A |
Terminal 2 West Pier | 3c(01) | 14.4 | 169.6 | 15,070 | 69,364 | N/A |
Terminal 2 East Pier | 3c(02) | 14.4 | 168.5 | 15,060 | 69,433 | N/A |
Coach Station | 3d | 8.3 | 161.8 | 8,675 | 49,172 | N/A |
Terminal 2 Plaza | 3f | 23.7 | 177.2 | 5,930 | 70,950 | N/A |
Luton DART Terminal 2 Station and Tunnel extension | 3g | 23.7 | 177.2 | 26,790 | 88,569 | Maximum volume relates to above ground areas only and excludes develop-ment beneath surface level |
Terminal 2 Support Buildings – Energy Centre | 3h | 12.8 | 167.2 | 11,265 | 95,983 | Maximum work area includes Terminal 2 Support Buildings – Service Yard |
Terminal 2 Support Buildings – Service Yard | 3h | 5.0 | 159.5 | Included in maximum work area for Terminal 2 Support Buildings – Energy Centre | 941 | N/A |
Terminal 2 Support Buildings – Emergency Vehicle Assembly Area | 3h | 5.0 | 159.2 | 4,858 | 2,047 | N/A |
Airport Operations and Maintenance | 3i | 15.2 | 168.7 | 22,100 | 335,478 | N/A |
Hotel | 4a | 22.0 | 175.5 | 9,441 | 45,980 | N/A |
Hangar A and B | 4b | 27.5 | 185.0 | 16,641 | 316,800 | N/A |
Fuel Storage Facility | 4c(01) | 24.2 | 151.4 | 83,700 | 459,800 | N/A |
Fuel Pipeline – above ground installation | 4c(02) | 4.6 | 140.4 | 8,355 | 38,600 | N/A |
Water Treatment Plant | 4d | 13.9 | 141.0 | 6,760 | 69,994 | N/A |
Solar Energy Battery | 4e | 7.2 | 139.8 | 5,270 | 37,681 | N/A |
Airside Security and Access | 4f | 5.0 | 158.0 | 2,870 | 545 | N/A |
Car Park P1 | 4g | 20.4 | 135.4 | 14,105 | 111,588 | N/A |
Car Park P5 – New Decked Car Park | 4k(02) | 7.7 | 163.2 | 22,536 | 147,303 | N/A |
Car Park P9 – New Decked Car Park | 4o(02) | 7.7 | 161.6 | 27,362 | 163,286 | N/A |
Car Park P10 – New Long Stay car park | 4p(01) | 5.0 | 142.0 | 28,969 | – | The maximum building height applies to the PV canopies, bus shelters and barriers within this work. |
Car Park P10 – Reconfiguration of New Long Stay Car Park | 4p(02) | 5.0 | 135.0 | 71,410 | 2,005 | The maximum building volume applies to the welfare buildings within this work. |
Car Park 11 – New Long Stay Car Park | 4q(01) | 5.0 | 137.0 | 45,045 | 2,797 | The maximum building volume applies to the welfare buildings within this work. |
Car Park P11 – Expanded Long Stay Car Park | 4q(02) | 5.0 | 137.0 | 51,789 | 644 | The maximum building volume applies to the welfare buildings within this work. |
Car Park P12 – New Terminal 2 Multi Storey Car Park | 4r | 17.1 | 170.6 | 25,070 | 315,205 | N/A |
Police Station | 4u | 12.1 | 173.5 | 6,780 | 14,520 | N/A |
Substation | 4w | 7.6 | 162.0 | 4,005 | 9,222 | N/A |
Substation | 4x | 7.6 | 162.1 | 3,600 | 12,144 | N/A |