ID badges: Hide | Show

SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 5PROCEDURE FOR DISCHARGE OF REQUIREMENTS

Interpretation

43.  In this Part of this Schedule—

Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—

(a)

Buckinghamshire Council;

(b)

Central Bedfordshire Council;

(c)

Dacorum Borough Council;

(d)

the Environment Agency;

(e)

Hertfordshire County Council;

(f)

Historic England;

(g)

Luton Borough Council;

(h)

National Highways;

(i)

Natural England;

(j)

North Hertfordshire District Council;

(k)

the relevant sewerage undertaker; and

(l)

the relevant water undertaker;

specified period” means a period of—

(a)

13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;

(b)

8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or

(c)

such longer period as may be agreed between the undertaker and the discharging authority.