SCHEDULE 2REQUIREMENTS

PART 2REQUIREMENTS PERTAINING TO CONSTRUCTION

Remediation of Former Eaton Green Landfill

18.—(1) No part of the authorised development comprising Work No. 1b may commence until—

(a)a remediation strategy;

(b)a foundation works risk assessment; and

(c)a groundwater, ground gas and leachate monitoring strategy,

for the former Eaton Green Landfill has been submitted to and approved in writing by the relevant planning authority, following consultation with the Environment Agency and the relevant water undertaker.

(2) The remediation strategy to be approved under sub-paragraph (1) must be substantially in accordance with the outline remediation strategy (for the former Eaton Green Landfill site).

(3) The foundation works risk assessment to be approved under sub-paragraph (1) must be substantially in accordance with the outline foundation works risk assessment.

(4) The groundwater, ground gas and leachate monitoring strategy to be approved under sub-paragraph (1) must be substantially in accordance with the outline strategy report for groundwater, ground gas and leachate monitoring strategy.

(5) Work No. 1b must be carried out in accordance with the remediation strategy, foundation works risk assessment and ground water, ground gas and leachate monitoring strategy approved under sub-paragraph (1).