SCHEDULES
SCHEDULE 1AUTHORISED DEVELOPMENT
Sitewide works to enable development
Work No. 1a — Within the area of land shown on the Works Plans as Work No. 1a, earthworks involving the excavation of natural material and existing made ground and stockpiles to create a new apron at approximately existing apron height as well as a landform platform suitable for the construction of a new terminal, apron, car parks and ancillary airport facilities.
Work No. 1b — Within the area of land shown on the Works Plans as Work No. 1b, landfill remediation works to the former Eaton Green landfill site including the excavation, processing and re-deposit of material and the piling of foundations to support the new airport buildings and infrastructure.