Construction travel plans
11.—(1) No part of the authorised development is to commence until a travel plan for the construction of that part which is substantially in accordance with the framework construction travel plan has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant local highway authority and where different, the relevant planning authority on matters related to its function.
(2) The authorised development must be carried out in accordance with the construction travel plan referred to in sub-paragraph (1).
(3) In this paragraph, “framework construction travel plan” means the document of that description listed in Schedule 16 (documents to be certified) and certified by the Secretary of State.