Traffic management

10.—(1) The preliminary works must be carried out in accordance with section 6 of the outline traffic management plan for construction.

(2) No part of the authorised development is to commence until a traffic management plan for the construction of that part which is substantially in accordance with the outline traffic management plan for construction has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant local highway authority and where different, the relevant planning authority and other bodies identified in Table 2.1 of the outline traffic management plan for construction on matters related to their functions.

(3) The authorised development must be carried out in accordance with the traffic management plan referred to in sub-paragraph (2).