SCHEDULES
SCHEDULE 15DEEMED MARINE LICENCE
PART 4CONDITIONS
Distribution of copies
9.—(1) The MMO must be notified in writing of—
(a)any agents, contractors or sub-contractors that will carry out any licensable marine activity listed in Part 4 of this licence on behalf of the undertaker and such notification must be received by the MMO no less than 24 hours before the commencement of the licensable marine activity; and
(b)any vessel being used to carry out any licensable marine activity listed in Part 4 of this licence on behalf of the undertaker and such notification must be received by the MMO no less than 24 hours before commencement of the licensable marine activity, and notification must include the master’s name, vessel type, vessel IMO number and vessel owner or operating company.
(2) The undertaker must ensure that—
(a)a copy of this licence and any subsequent revisions or amendments has been provided to any agents contractors or sub-contractors that will carry out any licensable marine activity listed in Part 4 of this licence.
(b)a copy of this licence and any subsequent revisions or amendments has been provided to the masters of any vessel being used to carry out any licensable marine activity listed in Part 4 of this licence, and that a copy of this licence is held on board any such vessel.
(c)mariners and fishermen’s organisations are made fully aware of the activities through a local notice to mariners issued at least 10 business days prior to the commencement of the licensed activities, or any part of them.
(3) The notice under sub-paragraph (2)(c) must—
(a)provide the start date of any licensed activities;
(b)be provided to the MMO Marine Licensing Team within 5 business days of publication.