SCHEDULES

SCHEDULE 15DEEMED MARINE LICENCE

PART 4CONDITIONS

Construction method statement

10.—(1) The undertaker must submit details of a method statement to the MMO for approval by the MMO at least 30 business days prior to the commencement of the licensable marine activity.

(2) Unless otherwise agreed by the MMO in writing, the method statement must include the following details—

(a)the details of the entity responsible for the carrying out of the licensed activity;

(b)a programme of works including the timings, duration and the location of the licensable marine activity;

(c)the detailed methodology to be employed by the undertaker in carrying out the licensable marine activity, including method of delivery to site and plant to be used during the licensable marine activities;

(d)contractor and vessel details;

(e)plans and sections;

(f)details of where the licensable marine activity was assessed in the Environmental Statement;

(g)details of materials to be placed in or removed from the marine area;

(h)environmental mitigation measures; and

(i)a lighting management plan if 24 hour working is required to undertake the licensable marine activity.

(3) The licensable marine activity must not commence until the MMO has approved in writing the submitted method statement.

(4) The licensable marine activity must be carried out in accordance with the approved method statement, unless otherwise agreed in writing with the MMO.