SCHEDULES
SCHEDULE 15DEEMED MARINE LICENCE
PART 4CONDITIONS
Construction method statement
schedule 15 paragraph 10 10.—(1) The undertaker must submit details of a method statement to the MMO for approval by the MMO at least 30 business days prior to the commencement of the licensable marine activity.
(2) Unless otherwise agreed by the MMO in writing, the method statement must include the following details—
schedule 15 paragraph 10 2 a (a)the details of the entity responsible for the carrying out of the licensed activity;
schedule 15 paragraph 10 2 b (b)a programme of works including the timings, duration and the location of the licensable marine activity;
schedule 15 paragraph 10 2 c (c)the detailed methodology to be employed by the undertaker in carrying out the licensable marine activity, including method of delivery to site and plant to be used during the licensable marine activities;
schedule 15 paragraph 10 2 d (d)contractor and vessel details;
schedule 15 paragraph 10 2 e (e)plans and sections;
schedule 15 paragraph 10 2 f (f)details of where the licensable marine activity was assessed in the Environmental Statement;
schedule 15 paragraph 10 2 g (g)details of materials to be placed in or removed from the marine area;
schedule 15 paragraph 10 2 h (h)environmental mitigation measures; and
schedule 15 paragraph 10 2 i (i)a lighting management plan if 24 hour working is required to undertake the licensable marine activity.
(3) The licensable marine activity must not commence until the MMO has approved in writing the submitted method statement.
(4) The licensable marine activity must be carried out in accordance with the approved method statement, unless otherwise agreed in writing with the MMO.