SCHEDULE 14PROTECTIVE PROVISIONS

PART 3FOR THE PROTECTION OF DRAINAGE AUTHORITIES

Expenses and indemnity

24.  Subject to paragraphs 25 and 26 and sub-paragraph 23(5)(b) (maintenance of drainage works), if, by reason of the construction of a specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes or land drainage is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker as soon as reasonably practicable to the reasonable satisfaction of the drainage authority and, if the undertaker fails to do so, the drainage authority may make good the impairment or damage and recover from the undertaker the expense reasonably incurred by it in doing so.