SCHEDULE 14PROTECTIVE PROVISIONS
PART 10FOR THE PROTECTION OF PORT OF TILBURY LONDON LIMITED
Accumulation and erosion
142.—(1) If during the construction of a specified work or protective work or in the carrying out of a specified function or after the completion of that work or function, there is caused or created an accumulation or erosion wholly or partly in direct consequence of its construction, the undertaker, if requested by PoTLL, acting reasonably, must remedy the accumulation or erosion to the extent attributable to the construction of the specified work or protective work and, if it refuses or fails to do so as soon as reasonably practicable, PoTLL may itself cause the work to be done and may recover the reasonable cost of doing so from the undertaker.
(2) For the purposes of sub-paragraph (1)—
(a)in the case of an accumulation, the remedy must be its removal; and
(b)in the case of erosion, the remedy must be the carrying out of such reconstruction works and other protective works or measures as PoTLL reasonably requires.
(3) In this paragraph, “erosion” means any fluvial, mechanical or other erosion, collapse, disturbance or destruction of the bed or banks of the river Thames or any quay or jetty or other structure of whatever nature within the Port.