SCHEDULE 14PROTECTIVE PROVISIONS

PART 10FOR THE PROTECTION OF PORT OF TILBURY LONDON LIMITED

Construction traffic management protocol within the Port

136.—(1) Before the commencement of any work constituting Work No. CA5 or ancillary to it, including preliminary works, the undertaker must submit a construction traffic management protocol to PoTLL for approval.

(2) The construction traffic management protocol must include—

(a)the security process to be followed by all vehicles accessing Work No. CA5 or otherwise travelling through the Port;

(b)the code of conduct to which the undertaker, its employers, agents and contractors will be held to whilst on the Port;

(c)procedures to be followed by all vehicles to ensure the Port and access to the Port does not become congested during any period in which the level crossing in the Port is in use;

(d)the procedures to be followed in an emergency;

(e)a suggested process by which advanced approval will be sought from PoTLL of the number of vehicular movements, including abnormal indivisible loads, expected to pass through the Port within a period to be agreed with PoTLL, and for updates to this information to be provided at the end of agreed period, for the next agreed period; and

(f)a suggested process by which variations to the numbers approved by PoTLL under paragraph (e) are to be approved by PoTLL.

(3) The approval of PoTLL under sub-paragraph (1) must not be unreasonably withheld but may be given subject to such reasonable modifications, terms and conditions as PoTLL may make for the protection of the Port and its tenants, including in respect of their current and future operations.

(4) The undertaker must ensure that its employees, agents and contractors comply with the agreed construction traffic management protocol within the Port and failure of an individual or body to comply with the construction traffic management protocol will entitle PoTLL to prohibit that individual or body from entering the Port.