SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

1.  In this Part of this Schedule—

asset management plan” means the document of that description certified by the Secretary of State as the asset management plan for the purposes of this Order under article 51 (certification of plans etc.) or any revision to it as may be agreed from time to time with the relevant planning authority;

biodiversity net gain report” means the biodiversity net gain report as certified by the Secretary of State as the biodiversity net gain report for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

code of construction practice” means the code of construction practice Part A and the code of construction practice Part B as certified by the Secretary of State as the code of construction practice Part A and the code of construction practice Part B for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

commissioning” means the commissioning process for the authorised development as described in the outline commissioning plan;

community liaison plan” means the document of that description certified by the Secretary of State as the community liaison plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

construction workers travel plan” means the document of that description certified by the Secretary of State as the construction workers travel plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

construction traffic management plan” means the document of that description certified by the Secretary of State as the construction traffic management plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time within the relevant planning authority;

decommissioning” means the process for decommissioning the existing Cambridge waste water treatment works as described in the outline decommissioning plan;

design code” means the document of that description certified by the Secretary of State as the design code for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

drainage strategy” means the document of that description as certified by the Secretary of State as the drainage strategy for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time within the relevant planning authority;

enabling phase” means the initial phase of the authorised development comprising the carrying out of the enabling works;

“enabling works” comprise the following works as more particularly detailed in paragraph 3.1.6 and paragraph 3.4.1 of chapter 2 (project description) of the environmental statement (Document number 5.2.2 as described in column (2) of Schedule 18)—

(a)

construction of a temporary construction access from Low Fen Drove Way and perimeter fencing;

(b)

establishment of construction compounds and offices;

(c)

construction of the permanent access road and its junction with Horningsea Road;

(d)

land drainage works;

(e)

provision of services;

(f)

visual mitigation planting;

(g)

vegetation clearance;

(h)

archaeological investigations;

(i)

mitigation works required by the construction environmental management plan pursuant to requirement 9(2)(a);

(j)

within the boundary of the existing Cambridge waste water treatment works forming part of Work Nos. 18, 25 and 28, the establishment of construction compounds, the provision of site welfare facilities, the provision of services and the commencement of shaft construction;

(k)

within the boundary of Work No. 33, the installation of up to 50 metres of the Waterbeach pipeline under and extending from both sides of the Cambridge to King’s Lynn railway line and construction compound; and

(l)

any earthworks necessary in connection with (a) to (k) above;

framework archaeological investigation mitigation strategy” means the document of that description certified by the Secretary of State as the framework archaeological investigation mitigation strategy for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

lighting design strategy” means the document of that description as certified by the Secretary of State as the lighting design strategy for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

odour impact assessment” means the document of that description as certified by the Secretary of State as the odour impact assessment for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

operational workers travel plan” means the document of that description certified by the Secretary of State as the operational workers travel plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline carbon management plan” means the document of that description certified by the Secretary of State as the outline carbon management plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline commissioning plan” means the document of that description certified by the Secretary of State as the outline commissioning plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline decommissioning plan” means the document of that description certified by the Secretary of State as the outline decommissioning plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline operational logistics traffic plan” means the document of that description certified by the Secretary of State as the outline operational logistics traffic plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline outfall management and monitoring plan” means the document of that description certified by the Secretary of State as the outline outfall management and monitoring plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline soil management plan” means the document of that description certified by the Secretary of State as the outline soil management plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

outline water quality monitoring plan” means the document of that description certified by the Secretary of State as the outline water quality monitoring plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

phase” means the enabling phase and any subsequent phase of the authorised development as described in the latest phasing scheme approved by the relevant planning authority under requirement 3;

preliminary odour management plan” means the document of that description certified by the Secretary of State as the preliminary odour management plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority;

wildlife hazard management plan” means the document of that description certified by the Secretary of State as the wildlife hazard management plan for the purposes of this Order under article 51 or any revision to it as may be agreed from time to time with the relevant planning authority.