SCHEDULES
SCHEDULE 17MISCELLANEOUS CONTROLS
Party Wall etc Act 1996
3.—(1) No notice under section 1(2) or (5) (notice before building on line of junction with adjoining land) of the Party Wall etc Act 1996(1) shall be required before the building of any wall in the course of the authorised development before completion of construction.
(2) Sections 1(6) (underpinning of adjoining buildings) and 2 (repair etc. of party wall: rights of owner) of the Party Wall etc Act 1996 shall not apply in relation to—
(a)anything used, or intended to be used, by the undertaker for the purposes of the authorised development before completion of construction; or
(b)land on which there is any such thing.
(3) Section 6 (adjacent excavation and construction) of the Party Wall etc Act 1996 shall not apply in relation to a proposal to excavate. or excavate to erect anything in the course of the authorised development before completion of construction.