SCHEDULES
SCHEDULE 1AUTHORISED DEVELOPMENT
Work No. 4 – INLET WORKS & PRELIMINARY TREATMENT
Inlet works structure to receive flows from Work No. 8, Work No. 16 and Work No. 35 and imported liquors including—
(a)two screenings handling plants;
(b)screen channel;
(c)grit removal chambers;
(d)flow measurement channel;
(e)grit handling plant;
(f)two odour control units and exhaust stacks;
(g)skip storage area;
(h)cess and septic discharge point; and
(i)connections to Work No. 6, Work No. 8, Work No. 13, Work No. 16 and Work No. 35.