ID badges: Hide | Show

SCHEDULES

SCHEDULE 1AUTHORISED DEVELOPMENT

Work No. 4 – INLET WORKS & PRELIMINARY TREATMENT

Inlet works structure to receive flows from Work No. 8, Work No. 16 and Work No. 35 and imported liquors including—

(a)two screenings handling plants;

(b)screen channel;

(c)grit removal chambers;

(d)flow measurement channel;

(e)grit handling plant;

(f)two odour control units and exhaust stacks;

(g)skip storage area;

(h)cess and septic discharge point; and

(i)connections to Work No. 6, Work No. 8, Work No. 13, Work No. 16 and Work No. 35.