ID badges: Hide | Show

SCHEDULES

SCHEDULE 1AUTHORISED DEVELOPMENT

Work No. 35 – WATERBEACH PIPELINE SPUR TO TERMINAL PUMPING STATION

Up to two waste water pipelines laid underground between Work No. 33 or 36 and Work No. 16 to facilitate a connection between the waste water infrastructure to be provided as part of the Waterbeach New Town development and Work No. 16 including—

(a)crossings using either pipe-jacking or horizontal directional drilling technique but otherwise laid using either open cut trenching or horizontal drilling technique;

(b)new accesses and access improvements;

(c)temporary shafts;

(d)horizontal directional drilling launch and exit pits;

(e)welfare, storage and laydown areas;

(f)temporary haul roads;

(g)construction compounds;

(h)dewatering, drainage works and restoration of existing land drainage;

(i)ditch crossing, diversion and associated protection works;

(j)mud and soil handling;

(k)associated infrastructure including air valves and other pipework fittings and fixtures;

(l)permanent accesses for future maintenance and replacement of the pipelines; and

(m)connections to Work No. 16 and Work Nos. 33 and/or 36.