SCHEDULES
SCHEDULE 1AUTHORISED DEVELOPMENT
Work No. 11 – SECONDARY TREATMENT (SETTLEMENT)
Final settlement including—
(a)up to 8 final settlement tanks including sludge management system;
(b)return activated sludge pumps including chambers;
(c)surplus activated sludge pumps including chambers;
(d)pumping station;
(e)chemical storage and ferric dosing plant;
(f)distribution chamber; and
(g)connections to Work Nos. 6, 8, 10 and 13.