SCHEDULES
SCHEDULE 1AUTHORISED DEVELOPMENT
Work No. 1 – HIGHWAY WORKS
Highway works the general arrangement of which is shown on sheet 1 of the highways plans including—
(a)reconfiguration of the existing signalised junction of B1047 Horningsea Road and A14 Junction 34 eastbound slip road to provide a signalised four-arm junction facilitating access to Work No. 2;
(b)widening of and improvements to the existing footway/cycleway on the western side of the B1047 Horningsea Road and Horningsea Road between the westbound on-slip at A14 Junction 34 and Low Fen Drove Way including the provision of a verge between the footway/cycleway and the main carriageway;
(c)provision of a new central island on Horningsea Road to facilitate pedestrian and cyclist crossing to new footpaths and cycleways to be provided as part of Work No. 23 and the new footway/cycleway to be provided at (d);
(d)a new footway/cycleway on the eastern side of Horningsea Road between Low Fen Drove Way and the new central island to be provided at (c) and connecting to new footpaths and cycleways to be provided as part of Work No. 23;
(e)replacement of the parapet on the A14 overbridge on the B1047 Horningsea Road and associated highway layout alterations;
(f)improvements to the existing pedestrian and cycle crossings at the junction of the A14 Junction 34 on and off slips on the B1047 Horningsea Road;
(g)alterations to the B1047 Horningsea Road and Horningsea Road;
(h)street lighting, signage and associated electrical equipment;
(i)reconfiguration of kerb lines; and
(j)connections to Work No. 2.