SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Surface water drainage
9.—(1) No part of the energy park works may commence, save for the preliminary works, until details of the permanent surface water drainage systems, including a future maintenance plan, have been submitted to and approved by the relevant planning authority following consultation by the undertaker with the lead local flood authority, Scunthorpe and Gainsborough Water Management Board and the Environment Agency on matters related to their function.
(2) The details submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in the indicative drainage strategy and the design process and codes set out in the design principles and codes.
(3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the development coming into operation and maintained as approved throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.