SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Lighting scheme
5.—(1) No part of the energy park works or railway reinstatement works may come into operation until a scheme for all permanent external lighting has been submitted to and approved by the relevant planning authority.
(2) The scheme submitted and approved under sub-paragraph (1) must be in accordance with the principles of the indicative lighting strategy and include measures to minimise and otherwise mitigate any artificial light emissions during the operation of the authorised development.
(3) The scheme must be implemented as approved prior to the coming into operation of the authorised development and maintained throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.