Commissioning

19.—(1) Notice of the intended completion of commissioning of Work Nos. 1 (ERF), 1B (CCUS) and 2(b) (CBMF) must be given to the relevant planning authority where practicable prior to such completion.

(2) Work No. 1B (CCUS) must be constructed and commissioned within 6 months of the commissioning of Work No. 1 (ERF) and Work No. 2(b) (CBMF) must be constructed and commissioned within 12 months of the commissioning of Work No. 1B except that these timescales may be amended where it has been demonstrated to the satisfaction of the relevant planning authority that the alternative timescales sought are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.