ID badges: Hide | Show

SCHEDULE 9Protective provisions

PART 7For the protection of the Environment Agency

Construction of protective works

schedule 9 paragraph 87 87.  Without limiting paragraph 86 the requirements which the Agency may have under that paragraph include conditions requiring the undertaker, at its own expense, to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—

schedule 9 paragraph 87 a (a)to safeguard any drainage work against damage; or

schedule 9 paragraph 87 b (b)to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of any specified work.