SCHEDULE 9Protective provisions
PART 13For the protection of Air Products (BR) Limited
Authorisation of works details affecting pipelines or protected crossings
schedule 9 paragraph 185 185.—(1) Before commencing any part of a relevant work, the undertaker must submit the works details to Air Products in accordance with paragraph 195.
(2) The works details submitted under sub-paragraph (1) will be treated as having been received by Air Products on the date—
schedule 9 paragraph 185 2 a (a)that the undertaker obtains written acknowledgement of receipt from Air Products; or
schedule 9 paragraph 185 2 b (b)two clear working days following the date that the work details were submitted under sub-paragraph (1),
whichever is earliest.
(3) The undertaker must as soon as reasonably practicable provide such further particulars as Air Products may, within 30 days from receipt of the works details under sub-paragraph (2), reasonably require.