ID badges: Hide | Show

SCHEDULE 2Requirements

PART 1Requirements

Interpretation

schedule 2 paragraph 1 1.  In this Schedule—

term aod AOD” means above Ordnance Datum;

term carbon dioxide storage permit carbon dioxide storage permit” means any carbon dioxide storage permit granted in terms of The Storage of Carbon Dioxide (Licensing etc.) Regulations 2010 or such other licence, authorisation or consent as may replace it;

term commissioning commissioning” means the process during which plant components and systems forming part of the authorised development, having been constructed or modified, are tested and verified to be in accordance with design assumptions and to have met the appropriate safety criteria, and are made operational;

term contaminated land contaminated land” has the same meaning as that given in section 78A of the Environmental Protection Act 1990(1);

term ctmp CTMP” means construction traffic management plan;

term demp DEMP” means decommissioning environmental management plan;

term discharging authority discharging authority” means any body responsible for giving any consent, agreement or approval required by a requirement included in Part 1 of this Schedule, or for giving any consent, agreement or approval further to any document referred to in any such requirement;

term lemp LEMP” means the landscape and ecological management plan;

term offshore pipeline and storage works offshore pipeline and storage works” means works for the offshore carbon dioxide transportation and storage infrastructure into which the authorised development will connect;

term relevant planning authority relevant planning authority” means–

(a)

Lincolnshire County Council, North Lincolnshire Council and North East Lincolnshire Council for the purposes of–

(i)

Requirement 6 (construction traffic)

(ii)

Requirement 7 (highway accesses)

(iii)

Requirement 8 (surface water drainage)

(iv)

Requirement 10 (archaeology)

(b)

East Lindsey District Council, North Lincolnshire Council, North East Lincolnshire Council and West Lindsay District Council for the purposes of–

(i)

Requirement 2 (time limits)

(ii)

Requirement 3 (stages of authorised development)

(iii)

Requirement 4 (scheme design)

(iv)

Requirement 5 (construction environmental management plan)

(v)

Requirement 9 (contaminated land and groundwater)

(vi)

Requirement 11 (landscape and ecological management plan)

(vii)

Requirement 12 (ecological surveys)

(viii)

Requirement 13 (construction hours)

(ix)

Requirement 14 (restoration of land)

(x)

Requirement 15 (operational phase mitigation plan)

(xi)

Requirement 16 (decommissioning environmental management plan)

term relevant planning authority and “relevant planning authorities” and “relevant planning authority” means Lincolnshire County Council, North Lincolnshire Council, North East Lincolnshire Council, East Lindsay District Council and West Lindsay District Council, as applicable; and

term requirement consultee requirement consultee” means any body named in a requirement as a body to be consulted by the discharging authority in discharging that requirement.