PART 6Miscellaneous and general
Planning legislation
article 43 43.—(1) Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as not being operational land) of the 1990 Act.
(2) Any planning permission which has been initiated prior to the commencement of the authorised development pursuant to this Order may continue to be lawfully implemented thereafter notwithstanding any physical incompatibility with the authorised development or inconsistency with any provision of this Order.
(3) As from the date on which the authorised development is commenced, any conditions of a planning permission granted pursuant to Part 3 (control over development) of the 1990 Act (whether express or otherwise) which relate to land within the Order limits or land adjacent to the Order limits cease to have effect to the extent they are inconsistent with the authorised development or with anything done or approved under the requirements in Schedule 2 (requirements).
(4) As from the date of this Order where planning permission (whether express or otherwise) is granted (whether prior to the date of this Order or after) pursuant to Part 3 of the 1990 Act in respect of land within the Order limits for development not forming part of the authorised development, the carrying out of development pursuant to such planning permission is not to operate to prevent the undertaker from carrying out further works for the development of the authorised development pursuant to the terms of this Order.
(5) Nothing in this Order restricts the undertaker from seeking or implementing, or the relevant planning authority from granting, planning permission for development within the Order limits.