2025 No. 527
Infrastructure Planning
The A12 Chelmsford to A120 Widening Development Consent (Corrections) Order 2025
Made
24th April 2025
Coming into force
25th April 2025
term the act term the 2024 order The A12 Chelmsford to A120 Widening Development Consent Order 2024 (“the 2024 Order”)(1), which granted development consent within the meaning of the Planning Act 2008 (“the Act”)(2), contained correctable errors within the meaning of the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received written requests from the applicant(3) and Essex County Council for the correction of errors in the 2024 Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authorities for the area in which the land to which the 2024 Order relates is situated, that the request has been received.
The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.
2008 c.29. Paragraph 1 of Schedule 4 was amended by paragraph 128(2) of, and paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to the Act which are not relevant to this Order.
As defined in paragraph 4 of Schedule 4 to the Planning Act 2008.