SCHEDULE 9Protective provisions

PART 6For protection of Railway Interests

schedule 9 paragraph 82 82.  The undertaker must give written notice to Network Rail if any application is proposed to be made by the undertaker for the Secretary of State’s consent under article 7 (benefit of the Order) of this Order and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—

schedule 9 paragraph 82 a (a)the nature of the application to be made;

schedule 9 paragraph 82 b (b)the extent of the geographical area to which the application relates; and

schedule 9 paragraph 82 c (c)the name and address of the person acting for the Secretary of State to whom the application is to be made.