SCHEDULE 9Protective provisions

PART 12For the protection of Immingham Oil Terminal operators

Authorisation of works details affecting pipelines or protected crossings

schedule 9 paragraph 166 166.  No part of a relevant work is to be commenced until one of the following conditions has been satisfied—

schedule 9 paragraph 166 a (a)the works details supplied in respect of that relevant work under paragraph 165 have been approved by the IOT Operators; or

schedule 9 paragraph 166 b (b)the works details supplied in respect of that relevant work under paragraph 165 have been authorised by an expert under paragraph 168.